|
 |
| New 220-kilovolt high-tension lines
are needed to connect the three regional
power networks that cover the country’s
electricity needs |
As economic
development accelerates, so does the demand
for electricity to power it. Angolas
Empresa Naciona de Electricidade (ENE, the
National Power Company) is rebuilding some
of the countrys most crucial infrastructure,
to meet the growing electrical needs of
the Angolan industrial and service sectors.
ENEs mission doesnt stop at
Angolas borders, however, and the
company is pursuing ambitious plans to develop
the electricity market throughout southern
Africa.
As the Angolan
national energy utility, ENE manages electricity
generation, transmission, and delivery nationwide
except for Luanda, where distribution
is handled by a separate enterprise. While
there are multiple small electricity systems
operating in Angola, three main power transmission
networks cover the country: the northern
system, supplying Luanda and Bengo, Malanje,
Kwanza Norte and Kwanza Sul provinces; the
center system, supplying Benguela and Huambo;
and the southern system supplying Huila
and Namibe. Three hydroelectric stations,
at Cambambe, Biópio, and Matala,
supply two-thirds of Angola's electricity
generating capacity, with the remainder
generated by local, mostly diesel-fueled,
thermal generators.
During the
struggle for independence and the civil
war that followed, components of the electricity
system fell victim to sabotage, attack,
or a lack of maintenance. A 2004 assessment
determined that nearly half of Angolas
transmission and distribution network was
in need of repair or replacement. Almost
everything is a priority, because of the
direct destruction caused by the war and
because of indirect factors like a lack
of maintenance says ENE Chairman Dr.
Eduardo Nelumba. The overload of the
remaining infrastructure is also a problem.
The equipment has to serve a much greater
number of customers, causing a lot of wear
and tear. The lack of a reliable electrical
system has had environmental consequences
for Angola as well, increasing consumer
reliance on biomass and wood fuels and inviting
deforestation.
To answer the
great present demand for electricity, and
lay the groundwork to meet future needs,
ENE is pressing forward with projects to
create new generating capacity. The enormous
Capanda dam and generating station will,
when complete, incorporate four 130-megawatt
turbines at its site nearly 200 miles east
of Luanda on the Kwanza River. With the
participation of Brazilian and Russian contractors,
the Capanda project is doubling Angolas
hydroelectric capacity and bringing 520
megawatts of electricity online. Other hydroelectric
projects, to rehabilitate the Mabubas, Matala,
Lamaum, and Biópio dams, will bring
these more modest facilities back online
and help promote development in the provinces
by supplying electricity to smaller cities.
 |
Eduardo Nelumba,
President of the Board of Directors-
ENE |
Generation,
however, is only one piece of the electrical
system, and new 220-kilovolt high-tension
lines are needed to connect the three regional
power networks get the power to customers.
Dr. Nelumba believes that the challenge
is not just to add new capacity but to rebuild
Angolas electrical system from the
ground up. We are working to build
a new line to transport all this energy
and make it available to supply the huge
demand for electricity in Luanda. There
are other constraints in the distribution
network as well, so we need to invest in
production, transportation and distribution.
ENE has partnered
with China National Machinery and Equipment
(CMEC) to rebuild both high-voltage lines
for long-distance transmission and medium-voltage
lines for local distribution, connecting
the hydroelectric generating station at
Cambambe with new substations in Luanda
and the provincial cities of Viana and Cazenga.
After only two short years of the EME-CMEC
effort, a modern, national electrical grid
has started to take shape.
The move from
an informal economy to a modern financial
system will help ENE recover costs and encourage
greater participation from international
partners. We have improved from a
collection rate of around 41 percent in
2004 to about 65 percent in 2006,
Dr. Nelumba says, but balancing a good return
with a price that Angolans can afford is
a delicate task. We have to make the
tariff attractive enough to attract investors,
to cover their operational costs and investments.
On the other hand, we have to be on the
consumers side and meet their needs
in order to convince them to pay for consumption.
ENE is installing electrical meters for
customers, and is experimenting with a prepaid
system in Cuende province to simplify payment
and increase compliance.
Angolas
image as an arid and flat country conceals
the true reality of its hydroelectric potential:
with plentiful rainfall, high mountains,
and large rivers, Angola has the third-largest
water resources in Africa. Exploiting even
part of the countrys 50,000 megawatt
hydroelectric capacity more power
than is currently generated in all of South
Africa could supply energy to the
larger Southern African Development Community
(SADC) through the proposed Southern African
Power Pool. Dr. Nelumba believes that the
Angolan electricity market can easily
expand to the SADC region, or even central
Africa. Energy interconnection deepens Angolas
integration with the region, and provides
a greater security in supply.
Dr. Nelumba
understands electricity as a necessary precondition
for other economic activities to even begin
in Angola, saying that you cant
even consider industrialization and development
without energy. The vision I have is of
a reconstructed Angola that ensures the
well-being of its people, and by this I
mean access to electrical energy, to health,
to education, to housing, and to drinking
water.
|